@diprjk @JKNC_ @OmarAbdullah @ErAaquibSWDeva @pddjkofficial Today, Hon’ble Minister for Power Shri Ali Mohammad Sagar Shb visited the 320 MVA, 220/132/33 kV GSS Alustang, where he was warmly received by senior officers of JKPTCL Kmr. The Minister directed the C.E, JKPTCL Kmr, 1/4
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice @pddjkofficial Shri Ashwani Kumar, Financial Commissioner (ACS), visited GSS Alustang to review two key transmission projects: 1.Augmentation of the station from 320 to 475 MVA and the
2. Proposed 400 kV D/C Alustang–Leh 1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @pddjkofficial Glad to share that today TLMD-VII Div.of JKPTCL Kmr took possession of the land for the proposed construction of 100 MVA, 132/33 kV GSS Hajin at Bandipora in presence of C.E JKPTCL Kmr. accompanied by S.E O&M Circle-II 1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @pddjkofficial @kpdcloffice Today, Hon’ble MLA Budgam, Shri Aga Syed Muntazir Mehdi, paid visit to the office chamber of C.E JKPTCL Kmr. to discuss the Right of Way (RoW) issue at Sharifabad in connection with the ongoing HTLS 1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @pddjkofficial @kpdcloffice C.E., JKPTCL Kashmir, accompanied by S.E., O&M Circle-I, paid a visit to GSS Tethar to review the ongoing works for augmentation of the Grid Sub-Station from 50 MVA to 70 MVA under the Capex Budget. 1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @pddjkofficial @kpdcloffice C.E,JKPTCL Kashmir, accompanied by S.E., O&M Circle-I, paid a visit to the Pir Panjal Range to review and ensure the timely execution of necessary works on the 220 kV Kishenpur–Pampore Transmission Line. 1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @pddjkofficial @kpdcloffice A pre-bid meeting was held today in the office of the C.E JKPTCL Kmr. regarding the project “Implementation of Advanced Smart Energy Metering infrastructure in GSSs of JKPTCL Kashmir for Proper Energy Accounting.”1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @pddjkofficial @ErAaquibSWDeva C.E JKPTCL Kmr. accompanied by the S.E O&M Circle-II,visited the site at Sanoor Kalipora to review the progress of the ongoing work for insertion of D+3 Tower in the 220 kV Zainakote–Amargarh T/L under Capex 2026-27 Scheme.
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice JKPTCL Kmr. today kick-started a 03 day Orientation Programme for newly recruited J.E’s .The inaugural session was graced by the worthy Financial Commissioner (ACS), J&K PDD, Shri Ashwani Kumar, IAS, as the Chief Guest.
1/3
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice The C.E, JKPTCL Kashmir, reviewed the progress of Priority-I works being executed under the Capex Budget 2026–27 across the Kashmir Wing. The meeting was attended by all SE’s, Xn’s and Technical Officers.During the review 1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice
As committed, the damaged 50 MVA, 132/33 kV Power Transformer at GSS Mattan has been successfully test-charged, restored, and put on load. The transformer is operating smoothly and satisfactorily.With this restoration 1/2
Er Aaquib S.W Deva retweeted
2/2 the original transformation capacity of 100 MVA at GSS Mattan has been fully reinstated. The available capacity is now adequate to cater to the Peak load demand, ensuring reliable power supply to the area.Kudos to the dedicated team of Engineers & Staff of TLMD-VI .
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @OmarAbdullah @AshwaniKumar_92 @ahsanpardesi It is a matter of great pride for JKPTCL Kashmir that Er. Aaquib Sultana Waheed Deva, Chief Engineer, and Er. Hur-e-Yasrab, Assistant Executive Engineer, have been felicitated by the Institution of Engineers (India) on the 1/4
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice Glad to share that the Augmentation of the 132 kV Alustang–Habak Transmission Line has been undertaken under the CAPEX Budget Scheme by replacing the existing ACSR Panther conductor with HTLS (High Temperature Low Sag) 1/3
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice In order to overcome the menace of ROW (Right of Way) issues in the execution of transmission line works and to expedite the diversion of various 220 kV and 132 kV transmission lines affected by the construction of Ring 1/3
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice Keeping in view the growing importance of Cyber Security in the Power Transmission sector, C.E. JKPTCL Kashmir arranged a detailed presentation in her office chamber by Airtel OT Securities.The presentation was attended by 1/3
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice C.E JKPTCL Kmr. accompanied by S.E O&M Circle-II paid a visit to 220/132/33 kV GSS Alustang in connection with the proposed augmentation of the said GSS from 320 MVA to 475 MVA under the Capex Budget 2026–27 . 1/2
Er Aaquib S.W Deva retweeted
Replying to @AshwaniKumar_92
@AshwaniKumar_92 @DivComKash @ErAaquibSWDeva @kpdcloffice The 50 MVA, 132/33 kV Power Transformer of GSS Mattan is presently undergoing final inspection at the factory site. The transformer is expected to be dispatched from the factory site within this week.
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @ErAaquibSWDeva @kpdcloffice
C.E JKPTCL Kmr. arranged a presentation by M/s SECURE Pvt. Ltd. to provide the core technical team with an overview of smart meters being installed at all (GSS) of JKPTCL Kmr.The presentation focused on the features 1/2
Er Aaquib S.W Deva retweeted
Replying to @diprjk
@diprjk @AshwaniKumar_92 @NHAI_Official @ErAaquibSWDeva Glad to share that the LILO of the 132 kV USHP–I Transmission Line for charging the 20 MVA,132/33 kV GIS Z-Morh intended to feed the Z-Morh Tunnel has been physically completed today in the presence of C.E JKPTCL (Kmr.) 1/2