Official account for the #InlandRail project. 🚆24hrs Melbourne ↔️ Brisbane

Australia
Joined September 2016
🚧 Big progress in Broadford, Victoria! Two new bridges swung into place, including a 36m structure weighing 265 tonnes at Short Street. 👉Learn more: inlandrail.info/4o564Fk #InlandRail #Broadford #Infrastructure
1
2
190
Big moves at Euroa Station in Victoria! An 800-tonne crane lifted six 43-tonne concrete sections for the new pedestrian underpass, improving safety and accessibility for all. 👉Learn more: inlandrail.info/3JREv4k #InlandRail #EuroaStation #Infrastructure
1
1
230
🚧 Pedestrian underpass works are underway at Benalla Station! In just 11 days, crews: ✅ Laid 1.3km of track ✅ Installed signals & 600m of drainage 👏 350+ workers on site 🎥 See what’s next 👉 inlandrail.info/3W55zQn #BenallaStation #InlandRail
1
158
We made a lot of progress in Victoria over the September track possession with the demolition of the Hamilton Street bridge in Broadford, Victoria.​ Removing 460 tonnes of bridge will make way for double-stacked trains to run from Melbourne to Brisbane.
1
3
206
You saw the bridge works in Broadford but what else has been happening across Victoria. Heaps! 600 workers achieved some major milestones during a track possession last month in Wandong, Broadford, Hume Freeway-Tallarook and Benalla.
3
148
Taking shape. 💪🏗️ The first two beams have been installed at the Hamilton Street bridge in Broadford, Victoria. Two 35.5 metre beams, each weighing 35 tonnes, were lifted into place by a 650-tonne crane. Alongside lowering the existing rail track, this new higher structure is vital in providing sufficient clearance for double-stacked freight trains. 🚆
1
131
Wangaratta Station Precinct: From vision to reality. Locals now enjoy better access, connectivity and liveability. Subscribe to stay updated 👇 🔗 inlandrail.info/4kuJQLe
3
4
242
Unlocking opportunities 🤝 regional Australia. We are committed to providing opportunities for local workers and businesses. Workers from our construction contractor McConnell Dowell share how they helped deliver infrastructure upgrades that are set to benefit their Wangaratta region well into the future. 👇
1
305
We're commencing Tranche 2 of the Victoria section of Inland Rail! 🎉 We've kicked off major construction on the first of eight Beveridge to Albury Tranche 2 sites, with the commencement of work in Euroa this month.
2
3
179
Major works on Tranche 1 in Victoria are wrapping up! 🎉🚆 Thank you to the community for your patience and support during this time.
1
2
123
The NSW/QLD Border to Gowrie section's draft revised Environmental Impact Statement is now open for public consultation. Learn more about the EIS 👉inlandrail.info/42VRo4n
2
2
159
ICYMI: The new Wangaratta Station platform opened in early April. A big thank you to the Wangaratta, Victoria, community for their patience during the upgrade works. Learn more about the works at Wangaratta Station here:  inlandrail.info/3Yw8UJy
1
177
A quick throwback to March, when we removed the Docker Street Footbridge in Wangaratta, Victoria. This work was undertaken to provide sufficient clearance for double-stacked freight trains.
1
3
233
In March, we completed a 60-hour possession in Euroa, Victoria. As part of this work, we upgraded the Birkett Street level crossing to support the traffic detour ahead of construction starting on Anderson Street Bridge.
3
2
164
The upgraded Seymour-Avenel Road bridge in Seymour has re-opened to traffic. Built in the same location, the new bridge is higher to allow sufficient clearance for double-stacked freight trains and minimises environmental impacts. Learn more 👉 inlandrail.info/4lvQpio
1
105
The new Wangaratta Station platform has welcomed its first passenger train – the V-Line service running from Melbourne to Albury. There is now safer and more accessible access to the platform via a new pedestrian underpass, ramps and lifts. More: inlandrail.info/4clcrjE
3
14
419
Wangaratta Station's new pedestrian underpass is now open and providing a safe pathway across the station precinct.
124
Just some of the work we accomplished in our March possessions in Victoria. 🚆 Over the course of 60 hours, we made great progress across Wangaratta, Benalla, Euroa, Broadford, Seymour, Tallarook and Wandong. ⚒️
1
2
170
Our team, alongside our contractors McConnell Dowell and John Holland, worked tirelessly to ensure all scheduled work was completed and we thank the local communities for their patience and understanding. Learn more 👉 inlandrail.info/4hHeorL
1
120
Another round of successful track possessions is done and dusted! 🧤 Over the weekend our teams worked hard across the Beveridge to Albury and Albury to Parkes sections of Inland Rail. 🛠️ Stay tuned as we share more of what we achieved during our March possessions.
1
89