The drainage for the track and football field is roughed in and getting ready for high jump and pole vault areas to be cut in at General Sherman.
The gym floor base and wood slats are getting acclimated at Thomas Ewing. Scoreboard, backboards and gym divider is also installed.
Spires Paving is on site at Thomas Ewing. The first layer of asphalt is going down at the front of the building.
6
A little cold doesn’t stop Summit and there contractors from getting more work done at Thomas Ewing. Drywall is going up quickly and the joint are being taped.
This picture is of the front of General Sherman and is showing the first floor of the 7th and 8th grade wing.
7
The General Sherman walls are being built. This is a picture from the back of the building. The raised gravel area to the right in this picture is the stage area.
3