Jesse retweeted
Jeeezus:
theglobeandmail.com/canada/a…
Jesse retweeted
We are pleased to announce our report analyzing the possibility of German restarts has been released this morning and covered in the German press.
We found that up to 18.7 GW of nuclear capacity could be brought online quickly and cost-effectively if swift action is taken.
NEW GERMANY RESTART REPORT: Restarting up to 18.7 gigawatts of Germany’s nuclear fleet is technically feasible, cost-effective, and supported by a majority of Germans.
Germany has an untapped energy resource at a scale matched nowhere else in the West. Per capita, the nuclear capacity Germany could add this decade is nearly an order of magnitude greater than what China is planning to.
Despite the nuclear phaseout, German law already allows work to begin on reactor restarts as long as the electricity is not sold before the law is changed.
In @RadiantEnergyG's most in-depth analysis of Germany’s reactor restart opportunity to date, we find that this program would be:
FAST: 5 reactors could be returned to service in less than 5 years, 14 reactors total in under a decade.
COST-EFFECTIVE: Every reactor studied could produce electricity well below current wholesale prices in Germany. With public financing, these plants could significantly undercut the inflation‑adjusted average of the 2010s.
CHEAPER THAN NEWBUILDS: The cost to bring back the 5 easiest-to-restart reactors is cheaper than any single Western nuclear newbuild currently under construction.
SUPPORTED BY THE PUBLIC: 61% of Germans support making use of existing nuclear in Germany, nearly three times the 22% who favor a complete phaseout and ban.
The missing ingredient remains political will.
In our conversations with the German Energy Minister, it was clear that with the right information, including a sober, accurate picture of what's actually possible, there's real interest in saving this energy supply.
Now, German nuclear industry leaders, several of whom informed our analysis, are urging support for restarts. In a letter sent to Chancellor Merz and members of Parliament, the authors wrote that “reactivating German nuclear power is technically a possible and sensible option,” attaching Radiant Energy Group's report for reference.
Germany once had one of the finest nuclear programs in the world. As more countries across the West recommit themselves to expanding nuclear, Germany has a unique chance to rebuild that expertise while directly addressing the energy cost and supply security issues it's facing.
Jesse retweeted
Replying to @EatParly
What other motives would lead you to allow people to commit infanticide without punishment?
Jesse retweeted
Taiwan’s nuclear phaseout created a vulnerability that now sits directly on top of the Qatar Ras Laffan force majeure.
The uncomfortable arithmetic is that the nuclear capacity Taiwan chose to retire is almost exactly equal to the LNG volume it imports from Qatar.
Taiwan imports roughly 35 percent of its LNG from Qatar. LNG now fuels nearly half of Taiwan’s electricity after the political phaseout of nuclear power. The island maintains only about eleven days of LNG storage.
Had Taiwan kept its full nuclear fleet operating and commissioned Lungmen, its completed but never fuelled fourth nuclear plant, the country would today have roughly 7,750 MW of nuclear capacity producing about 61 TWh per year, covering around 21 percent of the grid.
Replacing that output with gas requires far more primary energy because Taiwan’s combined cycle gas turbines operate at roughly 55 percent thermal efficiency. Producing 61 TWh of electricity from gas therefore requires roughly 110 TWh of fuel input, equivalent to about 10 to 11 billion cubic metres of natural gas or roughly 7 to 8 million tonnes of LNG per year.
That volume is almost exactly the amount of LNG Taiwan currently imports from Qatar.
In other words, the nuclear fleet Taiwan shut down would have displaced essentially the entire Qatari supply stream. Every cargo that does not need to cross the Strait of Hormuz is a cargo that cannot be held hostage.
Instead that capacity was retired and mothballed on political grounds and the gap was filled with gas.
On 23 August Taiwan held a referendum on whether to restart the Ma’anshan nuclear plant, the island’s last operating reactor station, which had shut down in May after its forty year operating licence expired.
A clear majority of participating voters supported restarting the plant subject to regulatory approval and safety confirmation.
Taiwan’s referendum law, however, requires affirmative votes from at least one quarter of all eligible voters, roughly five million people. The referendum received about 4.3 million yes votes, leaving it below the legal threshold and keeping the plant offline, effectively confirming the continuation of Taiwan’s nuclear phaseout.
Oil markets built resilience after decades of shocks. Strategic petroleum reserves, spare tanker capacity, and a deep spot market exist precisely because embargoes and supply crises forced the system to develop buffers.
LNG developed very differently. For most of its history it operated as a point to point business, the same ships on the same routes under long term contracts, functioning in conditions stable enough that nobody was forced to build equivalent shock absorption into the system.
Storage compounds this vulnerability and it divides sharply along geographic lines.
Europe benefits from geology. Depleted gas fields and salt caverns can hold months of supply, which is why European utilities spend the summer refilling underground storage ahead of winter demand.
Asia has no equivalent.
Japan, South Korea, and Taiwan depend almost entirely on above ground insulated LNG tanks at their import terminals, essentially the same thermos principle used on LNG ships. South Korea had roughly nine days of LNG supply when Ras Laffan went offline. Taiwan had about eleven days. Japan operates in a similar range.
These are operational buffers designed for a world of uninterrupted deliveries rather than strategic reserves designed to ride out supply shocks.
When a major node in the LNG system fails, there is no large fleet of idle ships ready to reroute, no spare liquefaction capacity waiting to fill the gap, and in Asia no underground storage that can stabilize supply while the market adjusts.
Taiwan’s nuclear shutdown therefore produced a structural vulnerability that is now impossible to ignore. The reactors that were closed would today be offsetting almost the entire volume of LNG Taiwan buys from Qatar.
There's never been a better time to restart Taiwan's nuclear fleet.
Jesse retweeted
OCAA then: you must build the Portlands gas plant!
OCAA now: you must shutdown the Portlands gas plant!
Great piece published in the Beach Metro about the insanity of hosting the city's largest polluter beside a new housing development. It's time to shutter the Portlands gas plant and replace it with wind and solar, storage and efficiency.
#topoli #onpoli
beachmetro.com/2026/03/08/le…
Jesse retweeted
No, if the degrowther Avi Lewis — who attacked blue-collar workers at what he called “big, manly” remote work “man camps” that have “intense, horrifying impacts” on indigenous women and girls, basically calling all these workers racists, rapists and murderers — it will be the final nail in the coffin for working-class support for the NDP.
That comment will go down as the NDP’s version of Hillary Clinton’s “basket of deplorables” moment.
What he said was definitely noticed in these camps (where I work as a geologist, as it happens) — not least by indigenous workers.
And you just know that the Tories were quietly storing away that statement to re-deploy again and again during any election campaign.
If Avi wins, there’s no coming back from that utterly disgraceful comment (which, by the way, also threw under the bus all the women who are in the trades, who are cooks, pilots, loggers, geologists, biologists and engineers).
But it’s not just the comment, it’s what it represents: it’s emblematic of Lewis’s eco-austerity, NIMBY agenda that opposes mining, nuclear plants, hydro dams, pipelines, sustainable logging, and even expanding building homes. It is the opposite of what a working-class party should be for. It destroys blue-collar jobs all the while, ironically, slowing down the clean transition.
How do we have public hospitals or homes, or electric buses and bicycles, or wind turbines or solar panels without the products of mining? How does Avi produce all his fancy campaign videos and documentaries without the minerals, metals and petroleum-chemicals that go into his video cameras?
The federal NDP will simply end up in the dustbin of history if Lewis wins the party leadership race.
NDP leadership candidate Avi Lewis says socialism, defined by bold public solutions, not managerial caution, can rebuild the party after historic losses.
He’s betting it can unite a majority across divided regions and broaden the party’s coalition. jacobin.com/2026/02/canada-l…
Jesse retweeted
The clean firm vs renewables debate is the defining backbone of energy twitter. Like in the old days, it was a constant war and fun to see it come up again.
Quick takes:
1. The cross-over point between firm and non-firm resources depends on how clean you want to get.
2. It also depends on the relative costs of the resources. The old debates were fun b/c costs were changing so quickly, where the optimal was being recalculated in real time. Some took this too far, others not far enough, this is the cause of most of the debate imo.
3. You can have 90% VRE+storage and still rely on thermals for 80% of your capacity needs. That's not contradictory!
4. You need to consider the whole system when designing a least cost system, including all physical constraints.
Let me provide a couple of heuristics.
A)If solar breaks $500/kW and storage under $100/kWh (total installed), you can hit 80-90% ish clean for a manageable premium (1-2 cents).
B) If you have great wind, 90% is in the cards.
C) If clean firm breaks $4k/kW, it's going to sweep in any region without wind.
D) If your long term goal is above 80% clean, you need to do long-term planning and consider clean firm up front, there is a shift at higher levels where you start shedding renewables and replace that (plus back-up gas) with firm.
E) (special) - generators in most cases do not directly experience system value, they experience market price. In the case of renewables, they diverge a LOT at higher levels, and so the "market saturation" may be a lot lower than the system models would predict.
Jesse retweeted
Here are the two core assumptions on which rests the prevalent desire in Canada's military establishment to continue with a single fleet of F35:
1) "it’s very likely that even the most right-leaning Republican candidates for elected office in the coming years will need to return to old orthodoxies on cooperation with allies, or otherwise face electoral irrelevance."
2) "given the damage wreaked on America’s international standing by Trump’s current posture, the U.S. will need allies more than ever".
In short, it rests on the belief that Trump is a blip, not a symptom of deeper trends. This belief is at best naive, at worse perilous. A defence policy should not be grounded on the hope of a better tomorrow.
We know the US society is deeply polarized and therefore highly volatile. This should be the basis on which Canada makes its foreign and defence policy. Discounting alternatives to the F35 as weaker and costlier fails to consider the costs of alignment on a unpredictable neighbour.
Richard Shimooka: A mixed F-35/Gripen fleet will fail us in every way
'The Gripen is less capable, more expensive and still reliant on U.S. production'
nationalpost.com/opinion/ric…
Jesse retweeted
I was honoured to be interviewed by @AtomicBlenderYT for this mini documentary on HALEU and the economics shaping the next phase of nuclear power.
A central theme of the film is whether advanced reactors are economically durable, beyond their technical sophistication.
The discussion brings together Michael Seely (Atomic Blender), Nick Touran, Ph.D, P.E. (What Is Nuclear?), Dan Leistikow (Centrus Energy), Michael Hewitt (ULC Energy), and myself from Decouple, with a focus on fuel cycle realities rather than design aesthetics.
One of the most important numbers in the HALEU debate is fuel cost. Fabricated HALEU currently sits around $30,000 per kilogram, compared with roughly $2,500 per kilogram for standard low enriched uranium fuel used in today’s light water reactors. That delta matters because one of nuclear power’s core value propositions has always been ultra high reliability paired with ultra low fuel costs, allowing plants to run at very high capacity factors with stable operating economics.
Advanced reactors will almost certainly require decades to approach the capacity factors achieved by the existing water cooled, water moderated fleet, which has benefited from generations of operational learning, regulatory familiarity, and incremental optimization. During that long maturation period, many of these designs will be operating with far more expensive fuel, tighter handling constraints, and less forgiving margins.
The combination of higher fuel costs and lower early capacity factors places real pressure on the economics of so called “advanced reactors”, particularly for bulk baseload electricity. HALEU may prove valuable for specific, high value, or space constrained applications, but fuel economics remain a decisive constraint when claims move from engineering promise to grid scale deployment.
Well worth watching for anyone interested in where advanced nuclear ambition meets the hard arithmetic of the fuel cycle.
youtu.be/O2JLbNDhoO4?si=DDqD…
Jesse retweeted
Last week @mattyglesias wrote an NYT Op-Ed arguing that Democrats should embrace the US oil and gas industry. As someone who's worked to advance clean energy for 15 years, I agree with him at least 80%. I agree for both technical and political reasons. 🧵
Jesse retweeted
Not everyone gets to visit the two new advanced AP1000 modular reactors at Plant Vogtle in the United States. This is your chance to see one up close, bricks size.
Real AP1000 units are now faster and more cost effective to build because of our modular design and mature supply chain.
Want to try building a bricks-size AP1000 reactor yourself? We're giving away another five Westinghouse bricks sets to people who reshare this post. We'll draw names on Monday from everyone who reposted! Can't wait to share the fun!
Jesse retweeted
What would geothermal power cost in Canada?
Local conditions have a big impact - but high temperature regions in BC and NWT are already competitive at costs of ~US$100 / MWh.
With innovation costs could fall to less than half that.
Jesse retweeted
The AP1000 Masterclass: Passive Safety, Industrial Memory, and the Return of Big Boring Reactors
Two years ago on @DecoupleMedia , @jbkrell and I recorded an episode with an aspirational title: American Nuclear, the Next Chapter. At the time it felt more like wishful thinking than reportage.
The conversation took place in a different climate. Investors and policymakers were fixated on small modular reactors, microreactors, heat pipes, and HALEU fuel. The “spaceX of nuclear” was a stock phrase. High profile people argued that a handful of lightly resourced startups would do for reactors what commercial launch companies did for rockets.
James ended that first episode with a prediction that sounded eccentric, if not slightly reactionary. If the United States wanted real new nuclear on the grid in the near term, he said, it should focus on building AP1000s and other existing large light water reactors like the ABWR in fleet mode, not chase vaporous concepts.
That was 2023.
In 2025 the picture looks different.
Vogtle 3 and 4 are finally online. Santee Cooper has selected @Brookfield to complete construction of the unfinished AP1000 units at V.C. Summer, and perhaps most significantly the Trump administration has announced an $80 billion strategic partnership with @WECNuclear to support the construction of new AP1000 reactors across the USA.
Three Mile Island Unit 1, an emblem of nuclear’s supposed decline, is back under a premium power purchase agreement with Microsoft. Data centers, cloud providers, and industrials are quietly telling developers what they actually want.
They are not buying “advanced nuclear” as a concept. They are buying high capacity factor megawatt hours and AP1000 is the only commercial scale Gen 3 plus reactor that can plausibly deliver those megawatt hours reliably on the first unit.
The Reliability Premium
The starting point for James’s argument is brutally simple: the market has re-discovered the value of a machine that runs near continuously.
Solar capital costs have fallen, storage costs have fallen, and for a 30 or 40 percent capacity factor you can carpet land with panels at a fraction of nuclear’s upfront bill. If all you want is energy some of the time, the toolkit is large.
What the last decade has demonstrated very clearly is that this does not solve the problem faced by hyperscale data centers and modern grids. They are not buying annual averages. They are buying 24/7 power.
That has two consequences.
First, there is now a genuine premium for high capacity factor energy. The Microsoft contract at Three Mile Island is a visible example, but similar deals are proliferating off stage. The buyers are sophisticated and willing to pay two, three, or four times wholesale prices for firm, clean megawatt hours.
Second, that premium is only justified if the technology can actually stay on 24/7/365.
Here the historical record is not kind to so called “advanced” reactor concepts.
Germany’s tiny 15MWe AVR pebble bed reactor, after years of operation, reached roughly a 62 percent capacity factor.
France’s 250MWe Phénix sodium fast reactor hovered around 40 percent, while 1242MWe Superphénix, the flagship, spent its short life near single digits.
Fort St. Vrain, the 330MWe prismatic high temperature gas reactor in Colorado, averaged close to 15 percent capacity factor, a level that genuinely could have been beaten by solar on the same site.
The unplanned outages that plague these “next generation” reactors, especially when scaled up in size, are particularly punishing for nuclear economics because the capital is sunk and the meter never stops running, while at least renewables are reliably unreliable, their variability is baked into project finance rather than blowing up the budget mid-stream.
By contrast, the mature American light water fleet, after many decades of trial and error, now runs at about 93 percent capacity factor on average. That is what is being monetized in these new contracts.
If your business proposition to a Microsoft, an Amazon, or a metals producer is “I can give you 90 percent plus capacity factor for decades”, then the technology has to be battle tested and more than a rendering. It has to carry industrial memory.
Among all the new reactor types vying for attention, only the AP1000 has any credible claim to that inheritance.
The paradox of the AP1000 is that it is called “advanced” in public discourse, but the nuclear steam supply system is intentionally conservative.
James describes it as a cafeteria reactor. Westinghouse did not attempt to reinvent the core, the coolant, or the thermo-hydraulics. Instead, it took the best proven elements from its own light water fleet and from the Combustion Engineering line, and recombined them in a way that would be familiar to any PWR engineer of the last forty years.
At the heart of the AP1000 lies a 157 fuel assembly core. The core geometry would be instantly recognisable to anyone who has worked on classic Westinghouse three loop plants. The main change is length. Instead of the more common twelve feet of active fuel, the AP1000 uses fourteen foot fuel assemblies, borrowing from designs such as South Texas Project, European plants like Doel and Tihange and any Combustion-Engineering System 80 core.
Move outward and the same pattern appears.
The steam generators are direct descendants of the CE “Delta 125” units at Arkansas Nuclear One Unit 2, updated but firmly within that lineage.
The pressurizer volume is comparable to South Texas Project, giving the AP1000 more margin for pressure and level transients than earlier designs.
The core barrel design tracks back to Waterford 3 and the broader CE family.
Even the hydraulic layout, a two loop arrangement with two reactor coolant pumps per steam generator, sits comfortably inside the range of existing practice.
In other words, the daily workhorse of the plant, the nuclear steam supply system that turns fissile heat into steam, is not radically new. It is a stitched together best of set drawn from thousands of reactor years of operation.
This is why units such as Sanmen and Haiyang in China, once they were finally completed, rapidly became some of the most reliable performers in the Chinese PWR fleet. It is why Vogtle’s units, whatever one thinks of the construction saga, are now slotting into the grid without commissioning dramas.
So if the AP1000 is conservative where it makes steam, where is the innovation?
The short answer is that Westinghouse innovated in the safety systems, partly to improve the safety case but primarily with the cost reduction motive of removing high CAPEX/OPEX active safety systems.
The AP600 came first, designed in the 1990s as a 600 megawatt electric plant with fully passive safety. No safety grade AC power. No safety critical emergency diesel generators. The design relied on gravity, large tanks of water, natural circulation, and clever thermodynamics rather than on motor driven pumps.
The AP600 never found a buyer. Suprise, surprise… economies of scale still mattered, and six hundred megawatts simply did not produce competitive power prices. The safety case, however, was a breakthrough.
By scaling AP600 up to roughly eleven hundred megawatts without enlarging the containment footprint, Westinghouse produced the AP1000. The diameter of the AP600 and AP1000 containment buildings is the same. Only the height and internal arrangement change. That is a rare case in this sector where scaling laws moved from conference papers to concrete.
The real novelty lies in how the AP1000 handles two categories of accidents that define any PWR’s safety philosophy: loss of coolant accidents, and station blackouts.
In a classical generation two pressurized water reactor, a large break loss of coolant accident is analysed as a race.
Lets walk through a hypothetical large guillotine break LOCA in a Gen-2 PWR. In this modelled scenario there is a complete severing of a hot or cold leg in the primary circuit. Primary pressure, initially around 2200 psi, collapses in seconds as water flashes to steam and vents into containment.
Nitrogen backed accumulators open automatically as the primary pressure falls below their setpoint, dumping borated water into the core region.
Within about ten seconds, high pressure safety injection pumps must start, powered from safety grade diesel generators that themselves must start, load, and sequence in very tight timelines.
Small and intermediate break LOCAs are more subtle. The leak is slower. Primary pressure falls more gradually and may never reach the accumulator setpoint in time. For those events, operators lean heavily on high head safety injection that requires AC power. If that power is lost, failures in seals on reactor coolant pump shafts can transform a station blackout into an unplanned LOCA of its own.
The AP1000 architecture is designed to remove as much of this race as possible. A few elements are central.
Core makeup tanks at system pressure
In addition to conventional accumulators, which sit at seven or eight hundred psi and only inject once the primary depressurises that far, the AP1000 uses core makeup tanks. These are small borated water tanks kept at primary system pressure, 2200 PSI, through direct communication with the pressure vessel through a cold leg.
In a small or medium break LOCA, they can begin injecting inventory into the vessel as soon as valve actuation logic demands it, long before the accumulated nitrogen tanks would open. No motor driven pump is required, only valves and the pressure differential created by the leak itself.
Automatic depressurisation and gravity feed from inside containment
If the system pressure does not fall fast enough, the automatic depressurisation system vents steam in stages from the pressuriser into a large pool of water inside containment, the in containment refuelling water storage tank (IRWST).
As pressure drops, the conventional accumulators open. When the primary is sufficiently depressurised, gravity from that same internal tank starts feeding water into the core region through dedicated injection lines. In later phases, water that has collected in the containment sumps is recirculated.
The key point is that all of this can proceed without safety grade AC. Motor driven injection is replaced by tanks, check valves, and height differences.
Canned pumps instead of seal packages
The AP1000 adopts canned reactor coolant pumps. Rather than a shaft penetrating a pressure boundary and relying on a complex seal package that itself needs injection flow during a blackout, the motor and impeller sit inside a common pressure housing.
Passive Residual Heat Removal (PRHR)
A final piece of the AP1000’s strategy for gaining 72 hours of operator free cooling in the race-against-residual decay heat time is the Passive Residual Heat Removal heat exchanger, the PRHR.
In a Gen-2 PWR, once the reactor trips on a LOCA or a station blackout, decay heat must be removed through active systems: auxiliary feedwater pumps, motor-driven residual heat removal pumps, and safety-classified cooling water systems. All of those depend, directly or indirectly, on AC power.
The AP1000 replaces that entire architecture with a submerged, naturally circulating heat exchanger, the PRHR, inside the In Containment Refueling Water Storage Tank (IRWST.)
When the reactor trips, hot primary coolant rises by natural convection through the PRHR loop, transfers heat into the large in containment water tank, and flows back down into the primary. There are no pumps, no diesels, and no operator actions in the time-critical window. The IRWST then vents this heat into containment as steam, which is ultimately rejected to the atmosphere through the passive containment cooling system.
Every watt of decay heat has to go somewhere. In Generation II plants, that usually means cooling towers or essential service water circuits that feed containment spray systems and residual heat removal exchangers. Those are active systems. They depend on pumps and on external water sources.
Here the AP1000 philosophy diverges completely.
In an accident, steam from a LOCA or from the passive residual heat removal (PRHR) heat exchanger fills the steel containment vessel. That vessel sits inside a separate concrete shield building, with an annulus between the two that is open to the atmosphere at the top.
On the roof of the shield building is a large tank of water. When passive containment cooling actuates, this water is released and flows over the outside of the steel shell as a thin film. Air drawn up through the annulus picks up the heat of evaporation and carries it away. The containment literally sweats. Gutters and downcomers collect part of the water and return it to internal storage.
The effect is to turn the containment shell into a giant vertical heat exchanger, transferring decay heat from the internal steam atmosphere to the outside air, using only gravity and natural draft. The system is sized to operate for seventy two hours without any AC power.
None of this is easy to calculate. Getting film condensation, natural convection, and complex three dimensional flows right in a safety analysis is non trivial. That is why the AP600 and AP1000 programmes included extensive integral test facilities and produced thick NUREG reports on scaling.
Once validated, however, the operating principle is simple. There is no dependence on safety grade AC and no need for safety classified cooling towers or ultimate heat sinks in the classical sense. The ultimate heat sink is the atmosphere itself, a far more elegant solution than say NuScale’s VOYGR plant which relies on what is probably one of the most heavily engineered and seismically qualified bathtubs on earth, a 75 foot deep, ten million gallon nuclear swimming pool in which the reactor modules are semi submerged.
A recurring line in Western nuclear commentary claims that the Nuclear Regulatory Commission still regulates reactors as if it were the late 1960s, unable or unwilling to accept passive concepts.
The AP1000 designs is a direct refutation.
This reactor could not have been licensed under the standards applied to the early fleet. The elimination of emergency diesels, the replacement of active spray systems with a passive containment cooling tank on the roof, and the heavy reliance on natural circulation for decay heat removal required entirely new validation methods and new rulemakings.
The Department of Energy funded the test facilities. Westinghouse and academic partners built and ran them. The NRC wrote new frameworks for how to treat passive safety systems, how to integrate them into probabilistic safety analysis, and how to credit them in the face of model uncertainty.
One can debate whether the broader licensing system is efficient. What cannot be claimed with a straight face is that nothing has changed. The AP1000 is concrete proof that the regulator will accept novel safety architectures when they are backed by data.
Most of the new companies pitching reactors in the West do not grasp the gulf between a credible safety case built on thousands of operating years and a set of simulations with limited test data.
Their slides often promise first commercial units this decade, at costs comparable to combined cycle gas, with construction schedules measured in two or three years and ninety percent capacity factors implied from day one. They assume worry-free cold and hot functional testing of their FOAK reactors as if they were a software alpha release.
The historical record for first of a kind nuclear plants suggests something different. Even with conservative design choices and large engineering teams, early years are often spent working through valve issues, instrumentation quirks, and thermal hydraulic surprises. Scaling factors that looked benign on paper reveal themselves. Capacity factors start low and climb only with time.
The AP1000 is not exempt from that history. Its first projects were late and over budget, largely due to civil construction and supply chain issues. What is notable is that once those units were completed, they behaved as they should like the light water reactors with familiar components that they were based on. They produced high capacity factors quickly because their cores, steam generators, and pumps were evolutionary, not revolutionary.
Westinghouse did not innovate in the parts of the plant that have to work flawlessly every day just to make steam. They did innovate in the parts that only matter in rare accidents, where simplicity and passivity can remove whole classes of failure.
If you strip away the branding, the AP1000 is not the future of nuclear in the sense that a marketing department uses that word. It is the logical endpoint of a specific light water reactor tradition.
It retains a conventional nuclear steam supply system, drawn from the best of Westinghouse and Combustion Engineering practice. It layers on top of that a safety system that assumes a station blackout from the outset, relies on tanks, gravity, and natural circulation, and removes most of the time critical AC dependencies that defined earlier designs.
It exists in the real world. It has units in operation in China and the United States. It has an industrial base that knows how to build its core components. It has a regulator that has already worked through the hardest questions of its safety case.
In a power system where the scarce commodity is no longer cheap electrons at noon but firm, clean megawatt hours at three in the morning, that combination matters far more than novelty.
If the use cases are sufficiently economically compelling, a big if, the “next chapter” for American nuclear power may eventually branch into so-called “advanced reactors.” These previously explored technologies failed to operate reliably and economically last century but with massive multibillion dollar R&D may at some point prove themselves. But the pages for the foreseeable future are being written by a nuclear steam supply system that looks, at first glance, almost disappointingly familiar.
Jesse retweeted
ASK AN ENGINE DESIGNER!
In an attempt to find out more about my audience (and to encourage more followers... *cough*), I will happy answer below (if I can) any question you might have about how engines are designed.
Note that I dont deal with the details of engine electronics much or mapping, so you wont find I know very much of interest there.
But I have been personally responsible for about 4 complete engines which were taken from not existing at all, to existing and running, and have designed at least one of most fundamental components, up to and including at F1 level (I`ve done one F1 cylinder head, a F1 geartrain), and a LOT of other bits and consultancy. I am also officially registered as an external consultant to the UK Govt Aircraft Accident Investigation Branch for certain historic aero engine failures (thankfully the only investigation I was called in to did not involve any fatalities other than the aircraft & engine themselves)
Normally people get charged a lot of money for advice like this so the only caveat is, you have to re-tweet this to ask a question.
If I know, I will answer it, however please do NOT ask for any very specific details about F1 stuff as NDA`s prevent me revealing company specific things, so dont ask me what kind of fuel injector spray pattern the Red Bull engine has, but do ask: "how on earth do you design a bolt ?" or more generally applicable questions.
Jesse retweeted
The US Nuclear Regulatory Commission provides a powerful legal barrier against antinuclear forces in the USA who seek to delay and destroy nuclear energy through legal uncertainty.
But now the NRC is under full-scale attack from a bunch of folks who don't seem to understand the crucial role the NRC plays in protecting nuclear energy from endless, arbitrary legal attack and investment-killing uncertainty.
Just a few minutes ago Republican Annie Caputo, perhaps the most pro-industry NRC commissioner of them all, resigned. @AlexCKaufman has the scoop. Caputo apparently resigned rather than be compromised by politics of NRC independence destruction.
The NRC helps ensure that there is only a tiny, extremely tough attack surface for antinuclear legal efforts to target. Running a reactor for 60 years? 80 years? There is very little that antinukes can do to stop it when the NRC says yes (and the NRC has agreed with its engineers and has said yes over and over).
Balkanizing nuclear regulation by handing it over to overworked and unqualified national or state-level bureaucrats and politicians radically expands nuclear's legal attack surface while making it thin and penetrable.
If I were at the Sierra Club or another antinuclear lobbying organization, I'd be delighted by the openings to attack nuclear energy this creates. You don't have to win your lawsuit against nuclear, you only have to delay it and add uncertainty to kill off a nuclear plant project. This was the playbook that the NRC killed off over time.
Does the NRC need to be reformed? Yes! Can it move faster? Yes! And this reform was happening and so is the speed-up. I've not met any serious, seasoned pro-nuclear expert who doesn't agree. But not a single one thinks the Commission itself should be politized or eliminated.
The NRC in the past has sharply limited the influence of antinuclear politicians from hurting nuclear.
Texas, for example, is attacking the NRC both from a "pro-nuclear" AND an antinuclear position! And we want to trust Texas non-technical lawyers and politicians to not abuse their nuclear power to hurt nuclear if it's politically expedient, as is happening now by trying to block a spent fuel storage facility?
And the vast majority of delays in developing and deploying new nuclear reactors have causes OTHER than the NRC. Developing nuclear reactors that function well is really hard! Building nuclear plants is hard! Blaming the NRC from the outside is easier than learning nuclear engineering or deployment history!
I hate seeing the current nuclear renaissance be jeopardized by ill-considered attacks on perhaps the most nuclear-friendly major regulator in the world.
I work on nuclear energy around the world and though the NRC isn't perfect, for those of us who love nuclear energy and want to expand it, it's better than pretty much any other regulator in a democracy.
I will be speaking out more publicly about this attack on nuclear energy's legal basis in the USA and I ask those who know the truth about this issue but who have not spoken out publicly to make your voices heard.
Jesse retweeted
1. Wind and solar both keep me up at night, but for opposite reasons. Solar works and is winning the global race, Britain simply sits too far north to benefit. Britain is betting on wind instead, yet wind lacks the very traits that makes solar work.
Jesse retweeted
Part of me has been feeling the time is approaching for a reckoning with the implicit solarmaxxing of both much of the Abundance movement *and* its critics.
The next 10 yrs is when these political groups must grapple deeply with the grid and power markets. 🧵
Certainly agree that there’s ample untapped room in most regions to get to that first ~30% of electricity from solar. Appreciate @_brianpotter's big caveats that his analysis didn’t cover transmission/distribution or power markets—indeed 2 key factors.
Some thoughts: 🧵
Jesse retweeted
Everyone says nuclear power is over-regulated. With word of the big nuclear EOs looming, I spent a few weeks talking to people in the nuclear industry to find out which reforms they thought would be most helpful, and which they were nervous about. Here are the top 12 (a🧵...)
Jesse retweeted
Once upon a time Saving Pickering was a fools’s errand and considered comically hopeless.
The supply chain was silent, afraid to antagonize Ontario Power Generation which had made up its mind to decommision the plant having purchased gas capacity to replace its output.
Even the unions who represented the thousands of workers about to lose their jobs had accepted “reality.”
Ontario was set to lose 1/4 of its nuclear capacity.
Into this hopeless environment entered an upstart non-profit founded in 2020, made up of passionate volunteer advocates called Canadians for Nuclear Energy.
We took up the fight.
Strangely enough we were discouraged from our activism by the nuclear industry itself. Ontario Power Generation, the Organization of Canadian Nuclear Industries and the Canadian Nuclear Association all attempted to call us off our goal.
When things felt hopeless (and they frequently did) our co-founder Christopher Adlam inspired us with his incredible conviction in what was right for the province its workers, our air quality and our medical isotopes industry.
The beloved and tragically prematurely departed legend, Howie Phorson, cheered us on from the sidelines.
We persevered.
We worked tirelessly with almost no budget assembling an entirely volunteer group of experts to produce the “Save Pickering” report complete with a technical appendix and a suggested refurbisment schedule.
Ontario hydro veteran @TomHess_ , Economist @E_R_Sepulveda, energy analysts @ScottLuft , Steve Aplin @cadlam and Paul Hader volunteered their time. Many more experts provided anonymous peer review.
The report, authored by @dylanjmoon was exceptionally argued and solidly researched.
We rallied the skilled trades and nuclear labour and got the report into the hands of provincial policy makers.
The International Brotherhood of @boilermakernews punched far above their weight.
Michelle Johnston courageously became the first union president to publicly call for the refurbishment.
The rest is history.
It is immensely satisfying to see the arguments we made in 2022 appear all over the media and in government announcements by @Sflecce and @fordnation in 2025.
In the words of Margaret Mead, “Never doubt that a small group of thoughtful committed individuals can change the world. In fact, it's the only thing that ever has."
The full report is linked in replies. Its worth a read.